Frequency of PAT testing
There are no absolute rules regarding the frequency of P.A.T Testing an item of electrical equipment should be inspected. HSE Guidance Notes which advised regular testing were generally interpreted as a requirement for annual testing however, circumstances and conditions of use will vary. The test persons should be able to advise on the frequency of testing from their own experience and discussions with the user or dutyholder regarding the lifestyle of the equipment. The repairer of equipment should test after repair. A hirer should test each piece of equipment before each hire contract.

All personnel responsible for the safe use of electrical equipment (e.g. contractors, managers of electrical/electronic laboratories, office managers, are each regarded by the EAWR as dutyholders and should operate a routine safety testing programme for equipment within their control and the periodicity of the tests should be based on the principles of risk assessment.

The HSE offer useful guidance in IND (G) 160L Maintaining portable electrical equipment in offices and other low risk environments.

The HSE advises: Experience of operating the maintenance system over a period, together with information on faults found, should be used to review whether and how often equipment and associated leads and plugs should receive a combined inspection and test.

The above advice offers only a starting point and should be modified by local judgements where necessary-i.e.Risk Assessment is required.

The following table shows the recommended times between tests, as laid out in the IEE guidance notes of PAT testing.

The IEE Suggested Initial Frequency of Inspection & Testing of Class 1 Equipment.

TYPE OF PREMISES
TYPE OF EQUIPMENT
FORMAL VISUAL INSPECTION
COMBINED INSPECTION & TESTING
Stationary equipment
24 months
48 months
IT equipment
24 months
48 months
Office & Shops Movable equipment
12 months
24 months
Portable equipment
12 months
24 months
Hand-held equipment
6 months
12 months
Stationary equipment
24 months
48 months
IT equipment
24 months
48 months
Hotels Movable equipment
12 months
24 months
Portable equipment
12 months
24 months
Hand-held equipment
6 months
12 months
Stationary equipment
Monthly
12 months
IT equipment
Monthly
12 months
Equipment used by the the public Movable equipment
Weekly
6 months
Portable equipment
Weekly
6 months
Hand-held equipment
Weekly
6 months
Stationary equipment
None
12 months
IT equipment
None
12 months
Industrial including commercial kitchens Movable equipment
Monthly
6 months
Portable equipment
Monthly
6 months
Hand-held equipment
Monthly
6 months
Stationary equipment
None
12 months
IT equipment
None
12 months
Schools Movable Equipment
4 months
12 months
Portable equipment
4 months
12 months
Hand-held equipment
4 months
12 months
Stationary equipment
Monthly
3 months
IT equipment
Monthly
3 months
Construction sites
110v equipment
Movable equipment
Monthly
3 months
Portable equipment
Monthly
3 months
Hand-held equipment
Monthly
3 months